The Port of Authority of New York and New Jersey says the excavation work for Towers 3 and 4 at Ground Zero, two nearly 80-story office towers at the World Trade Center site, have been completed. These sites have now been turned over to Silverstein Properties.

Over 13 months, the Port Authority excavated and constructed an entirely new 80-foot-deep foundation in concert with the continuing daily operations of the World Trade Center PATH Station moving 80,000 commuters a day. The project involved the removal of nearly 400,000 tons of concrete, soil and rock, the construction of an 80-foot-deep slurry wall and the installation of more than 240 steel tiebacks to hold that wall in place.

Since the Port Authority took over substantial responsibility for rebuilding in September 2006, all aspects of the site are moving forward.

In addition to completion of the excavation work for Towers 3 and 4, major construction at 1 World Trade Center, The Freedom Tower, continues with rising steel nearing street level and the building’s foundation and footings nearly complete. Construction of the foundations for the World Trade Center Transportation Hub and Memorial are also in progress.

Major steel beams for both projects will be erected during the upcoming year, and a new PATH station entrance is scheduled to open in the coming weeks, which will be in place until the Hub’s completion.

11:28 PM in Uncategorized, The Construction, World Trade Center, Related Stories, Freedom Tower News

Leave a Reply



(optional)


Related info: terrorism terrorist attack world trade center ground zero freedom world war 3 osama bin laden al qaeda 9/11 september 11 2001 america new york usa